| New property contracted |
Sept 20 |
| NR2 Architects contracted |
Sept 26 |
| Finalize floor plan and exterior elevations |
Oct 3 |
| Rendering complete |
Nov 4 |
| Construction documents complete |
Dec 12 |
| City of Richardson Permit application |
Dec 18 - Feb 28 |
| Construction bid phase |
Jan 15 - Mar 7 |
| Construction begins |
Mar 15 |
| TWC Move In |
Nov 15 |
|